Soil Ecology and Restoration Group |
Executive Summary
In August 1998, a 3.16 acre area on the Marine Corps Air Station Miramar (MCAS)
was cleared during fuel break and fire road maintenance. The area cleared was
covered with coastal sage scrub used as a home range for the endangered Polioptila
californica californica (California coastal gnatcatcher). To repair damage
to the area, the United States Navy signed a cooperative letter of agreement
with the Soil Ecology and Restoration Group (SERG) to install temporary erosion
control, revegetate and conduct native plant restoration research on the site.
In November 1999, SERG installed biodegradable straw flake dams to serve as
erosion control. Since then, sediment loss on the slope has been monitored with
aluminum erosion control monitoring pins. Only a negligible amount of sediment
has been lost from the site. In the spring of 2000, 1558 coastal sage scrub
seedlings grown in the SERG greenhouse at San Diego State University and the
SERG shadehouse at United States International University were outplanted. Seedlings
were irrigated throughout the summer. Vegetation surveys continued for the second
year and results for species percent cover and density were compared to those
from the reference site. The success criteria for this year was five percent
total species cover, a total species density of 1268 plants per hectare, and
100% container plant survival. The restoration site met the criteria for cover
and was an insignificant 2% behind on survival. The site also fell slightly
short of the required species density. We will wait until the results of next
year's survey to determine if action needs to be taken to increase density.
Results of soil analyses show that nutrient levels are beginning to return to
levels in the undisturbed areas. Next year, seedlings will be irrigated throughout
the summer months and monitoring of vegetation, soil nutrients, and erosion
will continue.
Introduction
Marine Corps Air Station Miramar, hereinafter referred to as the "Station",
is located on approximately 23,116 acres of land in San Diego County, California
four miles east of the Pacific Ocean and thirteen miles north of downtown San
Diego (Figure 1). In August 1998, a 3.16 acre area of undisturbed Diegan coastal
sage scrub inhabited by the California coastal gnatcatcher (Polioptila californica
californica) was removed by Station personnel during fuel break and fire
road maintenance. In September 1998, a cooperative letter of agreement with
Southwest Division, Naval Facilities Engineering Command and the Soil Ecology
and Restoration Group located at United States International University (USIU),
was signed to allow USIU to restore the impacted area and conduct native plant
restoration. The letter of agreement includes erosion control, weeding, container
planting, monitoring, and maintenance continuing through September 2002.
The focus of the project during the first year was on installing temporary, biodegradable erosion control, collecting seed, growing plants, and collecting initial vegetation and soil data for future reference. Signs designating the site closed to all forms of traffic were posted. Erosion control in the form of 39 straw flake dams was installed. Dams run perpendicularly to the road and are evenly spaced along the two sides of the slope. In addition to these activities, two small populations of Selaginella cinerascens (ashy spike-moss) were salvaged from the road widening construction area along Vega Drive in November 1998 and immediately transported to the R33 restoration site for replanting. Seven sections of ashy spike-moss, 20-30 cm long by 10-15 cm wide, were placed on the south section of the site and six on the north section. Each section was marked by a red flag. Two California sagebrush removed from the construction site were also transplanted on the R33 site.
In this, the second year of the project, over 1500 container seedlings were planted on site. Monitoring and maintenance activities continued (Tables 1 and 2) and will continue in much the same way for the two remaining years of the project.

Figure 1. Coastal sage scrub restoration site located on Marine Corps Air Station Miramar.
Table 1
Dates of site visits on the Station.
|
28 September 1999 |
Table 2
Names of personnel involved in the field and the greenhouse.
|
Site Description
The 3.16 acre site is located in the southeast corner of the Station on both
the north and south sides of fire road R33. The site is sloped approximately
20° to the southeast and is bordered to the east by a dirt road running north
and south along a riverbed. Disturbance to the site was due to the clearing
of vegetation via a chain pulled behind a vehicle in August 1999. In September
1999, vegetation remaining on the site consisted of a few Opuntia littoralis
(prickly pear cactus) and Eriogonum fasciculatum (flat-topped buckwheat).
Vegetation in the surrounding undisturbed area included Eriogonum fasciculatum
(flat-top buckwheat), Artemisia californica (California sagebrush), Malosma
laurina (laurel sumac), Salvia mellifera (Black sage), Baccharis
sarothroides (broom baccharis), Mimulus aurantiacus (monkey flower)
and exotic grasses such as Avena barbata (slender wild oat). The site
is in the home range of Polioptila californica californica (California
coastal gnatcatcher). Additional wildlife found on the site through visual sightings
or tracks include deer, rabbit, rattlesnake and coyote. The road on the site
is used by station personnel during security checks and occasionally by unauthorized
off road vehicle activity.
Methods
In the fall of 1999, a contractor was hired by the Navy to repair the R33 fire
road. This work resulted in damage to much of the restoration that had already
been completed at the site. Repairs to the road removed most of the straw flake
dams installed in November 1999 by SERG on the south side of the road. In the
spring of 2000, these dams were reinstalled. Additional repairs were made to
erosion gullies that had begun to form on the impacted area. These were filled
with straw bales and rocks to prevent further sediment loss.
In addition, the lower southeast portion of the site is now most likely severely compacted as it was used as a staging area and dump for excess gravel (see foreground of Figure 2). No plan was implemented to repair the damage to this area, such as ripping to reduce compaction and removal of the excess gravel, so it was decided that no coastal sage scrub seedlings would be planted in the area since they would be unlikely to grow.

Figure 2. R33 site after planting and installation of seedling shelters.
Planting
Between February and April 2000, a total of 1558 coastal sage scrub seedlings
were planted (Table 3). Planting holes were dug by hand and with a gas-powered
auger. Holes were pre-watered and plants were immediately installed and post-watered.
Basins approximately two feet in diameter were constructed around each plant
as a means of conserving water during irrigation. Each plant was given either
a TreePee or Tubex plant shelter to protect seedlings from herbivory and desiccation
(Figure 2).
Table 3
Coastal sage scrub seedlings planted in spring 2000.
| Species | Common Name | Feb/Mar 2000 |
April 2000 |
TOTAL (needed) |
| Artemisia californica Baccharis sarothroides Eriogonum fasciculatum Isocoma menziesii Lotus scoparius Malosma laurina Mimulus aurantiacus Nassella pulchra Ferocactus viridescens Rhus integrifolia Salvia apiana Salvia mellifera |
California sagebrush Broom baccharis Flat-top buckwheat Coastal isocoma Deerweed Laurel sumac Monkey flower Foothill needlegrass San Diego barrel cactus Lemonadeberry White sage Black sage |
302 8 165 12 40 23 74 155 4 80 125 102 |
203 7 43 5 18 8 24 104 - 15 15 26 |
505 (500) 15 (10) 208 (200) 17 (15) 58 (55) 31 (25) 98 (90) 259 (255) 4 (20) 95 (90) 140 (140) 128 (120) |
| TOTAL | 1090 | 468 | 1558 (1520) |
Maintenance
After planting, seedlings were watered twice each month through September when
seasonal rains began. Plants received 1/2 gallon per watering. Basins were filled
with hoses from a water tank located in the back of a pickup truck. Water was
obtained either from the fire pump located at the intersection of Green's Farm
Road and Ammo Road or from the Padre Dam water treatment facility. Selaginella
cinerascens patches were also watered. During trips to the site for irrigation,
plant protective shelters were removed from plants that had outgrown them and
"NO ENTRY" signs that had been removed by road construction contractors and
trespassers were replaced (Figure 3).

Figure 3. Installing "NO ENTRY" boundary sign.
In July 2000, in an effort to control weeds, approximately one-third of the seedlings were surrounded by straw mulch to a distance of one foot from the plant stem. Exotic vegetation was not sprayed with herbicide as permission for herbicide use was not obtained until 14 June 2000, but standing weeds were cut down using a gas powered weed trimmer (Figure 4). Cut weeds were bagged and disposed of offsite at the Miramar landfill.

Figure 4. Cutting down weeds with a gas-powered weed trimmer.
Monitoring
Documentary photos were taken throughout each stage of the project. Erosion
monitoring pins were checked for accumulated sediment monthly during winter
1999/spring 2000 and after each precipitation event greater than 0.5 inches.
In May 2000, ten soil samples, five from the site and five from the surrounding
undisturbed area, were collected and analyzed at A&L Western Agricultural Laboratories
for nitrate, total nitrogen, phosphorus, pH, and organic matter. On 29 May 2000,
estimates of species density and species percent cover were determined as well
as ground cover and percent survival of container plants. Vegetation surveys
were conducted according to a revised version of the California Native Plant
Society (CNPS) field sampling protocol. Percent cover was determined using two
100-meter transects, one on the south section of the site running east/west
at an angle of 84° and the second on the north section of the site running east/west
at an angle of 268°, with points every 0.5 meters (Figure 5). Species density
was measured by counting the number of plants within 2.5 m of each side of the
transects. Native and non-native herbs and forbs were measured using five one-meter
square quadrats. Selaginella cinerascens transplants were monitored for
health and survival.

Figure 5. 100-meter transect on the northern portion of R33 site.
Results
During the 1999/2000 rainy season, erosion monitoring pins were measured only
on the north side of the site where straw flake dams had not been damaged by
road repair work. Only 1mm of sediment was lost during the season. Deep erosion
gullies had formed on the south side of the site where dams had been destroyed.
Results of the chemical soil tests for samples collected on the restoration site and surrounding undisturbed area in November 1998, May 1999, and May 2000 are shown in Figure 6. Soil pH at the disturbed and undisturbed sites are nearly identical. Nitrates increased at both sites while total nitrogen decreased at the undisturbed site but stayed constant at the disturbed site. Available phosphorus increased at the undisturbed site and decreased at the disturbed site. Percent organic matter remained constant at the undisturbed site, but increased slightly at the disturbed site.



Figure 6. Soil test results on R33 restoration site and surrounding undisturbed area.
The results of this year's vegetation survey are found in Tables 4 and 5. Total species percent cover is 5%, total species density is 1020 plants per hectare, and percent survival of container plantings is 98%. All sections of S. cinerascens still appear alive and healthy. However, they dried out during the summer months, so it remains to be seen if they will green up again after winter rains. One of the two A. californica transplants is also still alive and healthy.
Table 4
Results of vegetation survey on R33 coastal sage scrub restoration site on 29
May 2000.
|
Species Species Substrate Forbs and Herbs |
Percent Cover Density (#/Ha) Percent Cover
Less than 1 |
Relative Cover Relative Density |
Table 5
Container plant survival as of May 2000.
|
Species |
Common Name |
Percent Survival 98 100 95 100 100 96 96 99 100 98 98 99 98 |
Discussion
This year's work focused on planting seedlings, irrigating through the harsh
summer months, and continuing to collect data on erosion, soil health, and transplant
success. The straw flake dams appear to be effective as a means of erosion control
since only 1 mm of sediment was lost from the north side of the site where dams
remained intact. In contrast, deep erosion gullies formed on the south side
of the site where dams had to be replaced.
Soil nutrient levels were initially similar in November 1998, only a few months after the site had been impacted. In the spring of 1999, the lack of vegetation on site was already having an impact on organic matter, nitrate, total nitrogen and pH. Soil samples analyzed this year were collected only two months after planting, so it was not expected that results would be drastically different than the previous year's results. However, results show that the initial drop in soil pH has reversed and is now virtually the same as at the undisturbed site. Nitrates, too, were falling at the disturbed site, but are now increasing again, just as at the undisturbed site. Total nitrogen levels were originally the same, then rose greatly at the disturbed site, and are now returning to normal levels. A similar path was followed by percent organic matter. Since all of these parameters are either similar to the undisturbed site or show signs of returning to normal levels, there appears to be no need for soil remediation. However, it is still early and a final decision should wait until we see if these trends persist. Phosphorus levels at the undisturbed site have remained fairly steady. However, at the undisturbed site, they are rising. If this trend continues, we will consider adding phosphorus to the disturbed site.
Initial vegetation surveys at the undisturbed site were used to establish success criteria for the restoration site. Success criteria for May 2000 are five percent total species cover, a total species density of 1268 plants per hectare, and 100 percent container plant survival. The restoration site meets the criteria for percent cover and, at 98%, is not significantly off in terms of survival. Vegetation survey results fall short for species density, but numbers are not low enough to cause any great concern. If density has not increased by the next sampling period in May 2001, then additional seedlings will be planted.
Selaginella cinerascens is a very slow-growing species, so it is difficult to assess transplant health by measuring anything more than simple survival. The transplants appear healthy so far and will continue to be monitored through 2002.
Conclusions and Recommendations
Straw flake dams proved to be an effective temporary biodegradable erosion control
method for the restoration site slope. For this project, the trenches into which
straw flakes were installed were dug by hand. In the future, it is recommended
that digging be done after the first winter rains to allow for easier manipulation
of the soil. Installing temporary fencing around future restoration projects,
particularly those in east Miramar, may reduce vandalism from trespassers and
possibly reduce damage to the site and plants from browsing by deer.
Changes seen in soil nutrients so far are short term with more significant changes in soil nutrients likely to appear over time. Future soil samples will be collected in May of each year through 2002 in order to record consistent, comparable results.
Initial surveys of undisturbed areas with characteristics, such as slope and aspect, that are similar to the restoration site is a valuable tool in determining success criteria for the restoration site as areas of coastal sage scrub vary in species composition, percent cover and density. Ensuring that results of yearly monitoring match the success criteria will aid in creating habitat similar to the habitat currently used by the California coastal gnatcatchers in the area.
Selaginella cinerascens appears to respond well to transplanting and may prove to be a useful method of erosion control. However, a longer, more in-depth study than the current one would be required to determine this. The survival of one of the A. californica shrub transplants suggests that it might be worthwhile to study the use of mature plants for coastal sage scrub restoration.
Next year's work will include continued monitoring of erosion, vegetation health and survival, soil nutrients, and Selaginella cinerascens transplant success. Seedlings will be irrigated once each month through the summer and plant protection will be removed as necessary. Approximately 16 Ferocactus viridescens that were not ready for planting during spring 2000 will be planted in the spring of 2001. In addition, since permission has now been received for herbicide application on Station, exotic vegetation will be sprayed with RoundUp Pro approximately twice this year. Further weed control efforts will include mulching around the remaining unmulched seedlings on site and cutting weeds with a weed whacker.
First Annual Report (January 13, 2001)
Final Report (February 17, 2002)